Hadley Complex Ballfield Lighting Replacement – Weekly Update (Week of May 26, 2025)
Here is the latest progress on lighting upgrades at the Hadley Complex ballfields:
Monday, May 26: No construction took place in observance of Memorial Day.
Tuesday, May 27: Lynco crews continued assembling light poles at Maag Field and successfully stood three poles at the Maag infield.
Wednesday, May 28: All remaining pole assemblies at Maag Field were completed. Crews also prepared designated areas at Paz Field for upcoming pole installations.
Thursday, May 29: Musco delivered the new lighting poles to Paz Field. Lynco began laying out the poles in their planned locations and continued standing additional poles at Maag Field.
Friday, May 30: Lynco is scheduled to complete setting all poles at Maag Field and begin assembling lighting poles at Paz Field.
Saturday, May 31: Work will continue at both fields. Lynco will start wiring the installed poles at Maag and continue assembling poles at Paz.
Monday, June 2: Pole base drilling is scheduled to begin at Harty Field. At the same time, pole assembly will continue at Paz Field and pole wiring will progress at Maag Field.
The full lighting package for Apodaca Field, including pole bases and light poles, is expected to arrive in mid-July.

Parks and Rec added: “Thank you for your continued patience!”